What does AND stand for in project management terminology?

Disable ads (and more) with a premium pass for a one time $4.99 payment

Study for the Certified Manager of Quality/Organizational Excellence exam with tailored questions and comprehensive explanations. Enhance your preparation with engaging learning tools.

In project management terminology, AND refers to the Activity Network Diagram. This diagram is a visual representation of the project's activities and how they interrelate, showcasing the sequence of tasks necessary to complete the project. It is a crucial tool for project managers as it helps in understanding the flow of activities, identifying dependencies, and scheduling tasks efficiently. By providing a clear visual layout, the Activity Network Diagram enables better communication among project stakeholders regarding timelines and project progress.

While the other options present definitions that might resemble project management concepts, they do not accurately define the established terminology commonly used within the field. The focus on activities, their order, and the relationships between them distinctly sets the Activity Network Diagram apart as the correct reference in this context.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy